Cobb County’s Hightower Trail Middle School was experiencing water infiltration through the built-up roofing, the metal roof panels, brick walls above the roofing, and the exterior insulation and finish system (EIFS) and windows at a center clerestory structure. Raymond provided A/E services associated with the roof replacement, replacement of the EIFS and windows at the clerestory, and modifications necessary to prevent water infiltration through the brick.
Client: Cobb County School District
Location: Marietta, GA
Size: 146,330 SF
Services Provided:
- Building Envelope Design
- Roof Replacement Design
- Testing
- QA/QC
- Construction Administration
- Project Management
Benefits/Challenges
Our Value Add
Raymond discovered possible infringements to the manufacturer’s warranty which provided the client with a functional and cost effective solution for their facilities.