Thomasville Primary School

Raymond provided the roof evaluation and roof replacement design for Thomasville Primary School. Our team recommended a gypsum cover board and PVC roof membrane system to increase building performance and promote future cost savings for the school.

Client: Thomasville City Schools
Location: Thomasville, NC
Size: 84,160 SF
Services Provided:

  • Roof Replacement Design
  • QA/QC
  • Construction Administration
  • Project Management

Benefits/Challenges

Unique Challenges

The initial design was based on the original construction documents and called for a replacement of the top course of CMU blocking. However, the construction phase revealed that the substrate was not adequate to secure the new blocking. Our design team worked with the contractor to identify an effective solution without costly change orders. The final solution involved Raymond determining which perimeter blocking areas could be corrected by tuckpointing the mortar joint versus areas that required a reset with new mortar. This allowed for much of the existing blocking to remain in place.

The project was originally scheduled as a summer construction project due to the break in the academic school year; however, the existing perimeter conditions did require additional time to be addressed to design specifications. Our team worked with the contractor to ensure that the safety plan properly accounted for all public areas and walkways so as to minimize overall disruption to the school operations. Additionally, all construction was coordinated with the owner to ensure proper communication of safety parameters. All re-roofing work was completed before the school year began.

Our Value Add

During our construction inspections, our team discovered that the cover board fastening was inadequate for wind uplift requirements. The team worked with the manufacturer to determine the optimal pattern and process for adding more mechanical fasteners.

Our initial site survey revealed that the existing insulation was an extruded polystyrene that could be reused during the project. This allowed the design to present multiple cost-effective options, and eventually enabled the owner to replace double the roof area as had been originally budgeted (i.e., the entire roof area).

Additionally, construction bid prices were lower than original cost estimates. This allowed the Raymond team to recommend a gypsum cover board and PVC roof membrane system, which is of higher performance and quality than the original TPO design alternative.

The contractor proposed to use the Rhinobond system (i.e., loose lay the membrane over the mechanically attached gypsum cover board and use induction welding to secure the membrane to the fasteners underneath). This method allows membrane securement without puncturing the membrane with fasteners or using costly adhesives. Our team reviewed the Rhinobond system and found it to be an efficient and simple solution for the school.